Project Overview

A beverage producer in Uzbekistan partnered with JNDTECH to build a complete carbonated drink filling line from the ground up. The goal: produce sparkling water and flavored CSD in PET bottles at 3,000 to 5,000 BPH, meeting local food-safety standards with a reliable, easy-to-operate line.

JNDTECH handled the full scope — water treatment, blow molding machine, isobaric carbondated water filling machine, labeling machine and shrink wrapping machine— and dispatched two engineers for on-site installation and commissioning over approximately 30 days.

Equipment Configuration

The complete line was configured as follows:

  1. Water treatment system — RO purification to prepare process water for carbonation and bottle rinsing.
  2. Fully automatic PET blow molding machine — produces bottles in-house from preforms, ensuring consistent bottle quality and lower logistics cost.
  3. Isobaric carbonated drink filling machine — 3-in-1 monoblock (rinsing, counter-pressure filling, capping) at 3,000-5,000 BPH for PET bottles 250ml-2L. Low CO2 loss, accurate liquid level.
  4. stricker Labeling machine — applies brand labels to finished bottles.
  5. Shrink wrapping machine — bundles bottles into retail-ready multipacks for distribution.

On-Site Installation

Two JNDTECH engineers arrived on site and completed the full installation in approximately 30 days:

  • Week 1: water treatment installation and piping; blow molder assembly and mold testing.
  • Week 2: filling monoblock positioning, conveyor connection and utility hookup (power, compressed air, CO2).
  • Week 3: line integration, labeling and shrink wrapper setup, full-line dry and wet runs.
  • Week 4: production testing with actual product, speed optimization, operator training and handover.

Project Photos

Below are scenes from the installation and commissioning.

Customer and JNDTECH team

Production line site

Results

  • Line running at rated 3,000-5,000 BPH within the commissioning period.
  • Stable carbonation with low CO2 loss, meeting the customer's fizz specification.
  • Operators trained to handle daily changeover and basic maintenance.
  • Full handover documentation provided, including electrical diagrams and maintenance schedule.

Why the Customer Chose JNDTECH

  • Complete turnkey supply — one supplier for the entire line, simplifying coordination.
  • On-site engineers — two technicians stayed for the full 30-day commissioning, not just a brief visit.
  • Local after-sales support — remote troubleshooting and spare-part supply after handover.

Start Your Own Line

Planning a carbonated drink or bottled water plant in Central Asia? Tell us your target capacity and product type. Contact JNDTECH for a free layout design and quotation.

Interested in This Solution?

Our engineers will prepare a tailored proposal and quotation for you.

Send Inquiry